PM Forecast

Modified on Fri, 23 Jul 2021 at 01:56 PM

  1. Click Maintenance | Preventive Maintenance | Forecast 

  2. Choose your Schedule Type from the drop down list 

  3. Select the date you wish to forecast through with the Generate through feature

  4. If you're forecasting On Demand PM's choose the On Demand Group from the drop down list

  5. Click Process

The results displayed are the number of Work Orders that would be Generated by PM Work Order Generation       