Adding Meter Based Schedule Records to a Pm Master Job

Modified on Fri, Jul 23, 2021 at 1:55 PM

NOTE: This can only be done to meter based PM Jobs

 

  1. Click Maintenance Preventive Maintenance | Search 

  2. Select the PM Master Job ID from the Search Grid

  3. Click Add Schedule Record 

  1. Select a Charge Type from the Charge Type dropdown list

  2. Select a Charge To by clicking the magnifying glass or the tree and selecting a record 

  3. Select a Meter from the Meter dropdown list

  4. Enter a Last Due meter reading

    NOTE: This should be the last time the PM was performed

  1. Enter the Perform Every interval

    NOTE: This should be how often the PM should be performed

  1. Select a Mechanic from the Assigned To dropdown list

  2. Select a Priority from the Priority dropdown list

  3. Select a Work Order type from the Type dropdown list

  4. Select a Shift from the Shift dropdown list

  5. Click Save to update the PM Master with the new Meter Based Schedule Record

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article