NOTE: This can only be done to meter based PM Jobs
Click Maintenance | Preventive Maintenance | Search
Select the PM Master Job ID from the Search Grid
Click Add Schedule Record
Select a Charge Type from the Charge Type dropdown list
Select a Charge To by clicking the magnifying glass or the tree and selecting a record
Select a Meter from the Meter dropdown list
Enter a Last Due meter reading
NOTE: This should be the last time the PM was performed
Enter the Perform Every interval
NOTE: This should be how often the PM should be performed
Select a Mechanic from the Assigned To dropdown list
Select a Priority from the Priority dropdown list
Select a Work Order type from the Type dropdown list
Select a Shift from the Shift dropdown list
Click Save to update the PM Master with the new Meter Based Schedule Record
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article