Adding an On Demand Schedule Based Record

Modified on Fri, 23 Jul 2021 at 02:17 PM

NOTE: This can only be done to a PM type of "on demand"

  1. Click Maintenance Preventive Maintenance | Search 

  2. Select the PM Master Job ID from the Search Grid

  3. Click Add Schedule Record 

  1. Select a Charge Type from the Charge Type dropdown list 

  2. Select a Charge To by clicking the magnifying glass or the tree and selecting a record

  3. Select an On Demand Group from the On Demand dropdown list

  4. Select a Mechanic from the Assigned To dropdown list

  5. Select a Priority from the Priority dropdown list

  6. Select a Work Order type from the Type dropdown list

  7. Select a Shift from the Shift dropdown list

  8. Click Save to update the PM Master with the new Meter Based Schedule Record

 

Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select atleast one of the reasons
CAPTCHA verification is required.

Feedback sent

We appreciate your effort and will try to fix the article