Formal planning can be very helpful in streamlining the work order workflow. This article describes how to update the schedule for work orders or update the work order hours in your plan.
For more help with formal planning in general, see Formal Maintenance Work Order Planning and Scheduling.
NOTE: You cannot change the personnel that the work order is assigned to within the resource list tab. To change personnel, you must schedule work orders in the planning tab.
Scheduling Work Orders Using Formal Planning
- To access the planning module, select Maintenance, then Work Orders, then Planning.
- Select the ID of the plan you'd like to schedule. If you cannot find the plan, use the filters to broaden or refine your search.
- The planning tab should open automatically. At the top menu, select Resource List.
- To update the scheduled date, select the scheduled column. A calendar will appear for you to select the date you would like the work to be done on.
- To update the hours, directly type in how many hours you expect the work order to take to be completed then click outside of the entry. The entry has been updated when the green circle with the check appears.
Was this article helpful?
That’s Great!
Thank you for your feedback
Sorry! We couldn't be helpful
Thank you for your feedback
Feedback sent
We appreciate your effort and will try to fix the article