  1. Click Maintenance | Preventive Maintenance | Search 

  2. Click on the PM you’d like to change

  3. Click Edit 

  4. Click the dropdown menu for “Schedule Type” and select On Demand 

  5. Click Save

  6. Scroll down to Schedule Records and click the pencil 

  7. You will now be required to select an on demand group

  8. Once you have done so, click save