Preventive Maintenance Work Order List

Modified on Mon, Sep 23 at 10:59 AM

This report provides a list of PM-based work orders generated through PM Generation or through meter readings and can be found under the work order reports category from the left menu.


First, select the date range you'd like to generate the report through. Below is a sample of what your report may look like:



You may customize your report by choosing which columns are shown and where by selecting the Configuration Icon in the top right. A quick tutorial is shown; for more help see Customizing Reports:



Finally, the chart below provides descriptions of the columns:


ColumnDescription
Work Order IDID of the work order being canceled.
Charge ToAsset ID the work order was charged to.
Charge To NameAsset Name the work order was charged to.
DescriptionDescription of the work order.
Create DateDate the work order was created.
Schedule DateDate the work order is scheduled to be completed on
Initial Schedule DateInitial Schedule Date of the work order from the PM system
Required DateDate the work order is required to be done by.
Complete DateDate the work order was completed.
Type & Type DescriptionWork Order Type and Type Description
StatusStatus of the work order in the Work Order Workflow.
ShiftShift the work order was scheduled for.
Completed ByPersonnel that completed the work order.
Down RequiredWhen this is Checked the Asset must be Down to perform the work
Priority
Indicates the order in which work orders should be completed based on their importance, criticality, and impact
Created ByUser that created the work order.
PM IDID of the PM job.
PM DescriptionDescription of the PM job.
PM Schedule TypeTrigger for the PM (Calendar, Meter, On Demand)
PM Frequency TypeUnits of measure for the frequency for calendar based PMs (days, months, etc).
PM FrequencyFrequency/how often the PM job should occur for calendar based PMs.
Requestor, Requestor Phone & EmailName, phone, and email the work order was requested by.
Scheduled DurationExpected duration of the work order.
Actual DurationActual duration of the work order.
Failure CodeType of Failure that occurred for this work to be performed
Action CodeAction that was taken to correct the Failure
Root Cause Code
What actually caused the Failure
Total WO CostTotal cost of the work order.
Account NumberAccount the work order was linked to.
Source TypeThe SOMAX type this work order was created from Ex: PM or Work Request
Department, Line, System (or your own Asset Groups 1, 2, and 3)The asset groups that you have created. For example, your asset groups may be department, line, and system. For more help with asset groups, see Setting up Site Details.
CommentsComments added to the work order
Assigned ToUser(s) who are assigned to complete the work order


Was this article helpful?

That’s Great!

Thank you for your feedback

Sorry! We couldn't be helpful

Thank you for your feedback

Let us know how can we improve this article!

Select at least one of the reasons